Tiers let a patch roll out progressively rather than everywhere at once — a pilot group first, then staging, then production — with gates between each stage. A policy uses tiers when its use tiered rollout option is on.

what a tier is​

FieldNotes
NameFor example Pilot, Staging, Production
Level1 is testing, 2 is staging, 3 is production. Lower levels deploy first, and the highest level is the default tier
Description—

how a device gets its tier​

Every Windows device belongs to exactly one tier, worked out in this order:

  1. Its own tier — the device was assigned to a tier directly.
  2. Its location's tier — otherwise, the tier its location is assigned to.
  3. The default tier — otherwise, the last tier: the one with the highest level, usually production.

So a device nobody has placed is not left out of a tiered rollout; it is patched with the last tier. The Tiers tab marks that tier with a default badge.

A device assigned directly stays in its tier even when its location is assigned to a different one.

A tiered policy with no tiers installs nothing

If Use tiered rollout is on but your organisation has no tiers, there is nothing to roll out through, so the policy installs nothing rather than patching every device at once. Create the tiers, or turn tiered rollout off.

assigning devices and locations​

Open a tier's … menu on the Tiers tab and choose Assign devices. The dialog has a devices tab and a locations tab, with one search box across both. Each device shows its current tier, marked "(via location)" or "(default)" where it did not get it directly.

Tick devices or whole locations, then Save assignments. Select all N shown and Clear shown act on whatever the search is currently showing.

A device or location belongs to one tier, so ticking it here moves it out of any other tier. Unticking a device and saving removes its own assignment, and it falls back to its location's tier or the default.

Assigning tiers needs patch:create.

moving devices from the devices list​

To move many devices at once, select them on the devices list and choose Patch tier in the bulk actions toolbar. Pick a tier to move them into, or Clear tier (use location / default) to remove their own assignment so they follow their location's tier or the default.

Moving devices into a tier adds them alongside its existing members, and takes them out of any other tier they were assigned to. The Patch tier button only appears for users with patch:create.

device counts​

Each tier on the Tiers tab shows how many devices it holds and how they got there, for example "5 devices · 1 assigned, 2 via location, 2 by default". The tier flow along the top shows the total as a badge on each tier.

the gates​

Each tier carries its own controls governing whether, and when, a rollout progresses to the next one.

ControlEffect
Require approvalBlocks promotion entirely — see below
Auto-promoteMust be on for a tier to progress at all
Minimum success rateThe success rate that must be met before promotion
Minimum test durationHours the tier must soak before it can promote

The gates are checked in that order, and the first one that fails stops the evaluation. They do not combine into a single balanced judgement: Require approval is tested before anything else, so when it is on, the success rate and soak duration are never reached.

A tier with Require approval on will never promote

Require approval is on by default for a new tier. There is no approval control anywhere in the product — no button, no page, no notification. Nothing can release a rollout waiting on it.

It is therefore a permanent stop rather than a pause. The only way to let a tier progress is to edit the tier and switch Require approval off.

Because Auto-promote is off by default as well, a newly created tier is blocked twice over. Both must be changed before a rollout can move on.

info

Tier progression is evaluated every 5 minutes. A tier that has met its gates will not promote instantly; it promotes on the next evaluation cycle.

how the gates interact​

Once Require approval is off and Auto-promote is on, the remaining gates are evaluated in this order:

  1. All tasks in the tier must have finished — nothing still pending, in progress or rebooting.
  2. At least one device must have reported a result.
  3. Minimum success rate — blocks promotion until enough devices have succeeded.
  4. Minimum test duration — requires the tier to have been running for a number of hours, counted from when that tier's first device was sent its patches.

Only when all four are satisfied does the tier promote, and the policy's install window can still defer the actual dispatch: promotion waits until the window is open.

The last tier has no gates. Once every one of its tasks has finished, the rollout completes, whatever that tier's own settings say.

tip

A soak duration is what actually catches patch problems, because the failures that matter often appear hours after a successful install — on the next reboot, or the next trading day. A pilot tier that promotes as soon as installs report success has tested that the patch installs, not that it is safe.

Set minimum test duration long enough to cover a full trading day on the pilot group.

empty tiers​

A rollout starts at the first tier that has something to install. If every pilot device is already patched, the rollout begins at the next tier with work instead of waiting on an empty pilot.

The same applies on promotion: tiers with no devices needing the patches are skipped, and a rollout with nothing left for any later tier moves to the last tier and completes.

watching a rollout​

The Overview tab of patch management shows Deployment Tier Progress: per tier, the name, a level badge, patched and total devices, a progress bar, the success rate, and the last deployment.

That success rate is what the minimum-success-rate gate is measured against.

caution

If a rollout appears stalled at the pilot tier, check its tier settings before looking for a fault. Require approval being on, or Auto-promote being off, will hold it there indefinitely — no notification arrives, and it does not time out into promoting.

Neither state can be cleared from the rollout itself. Edit the tier.